Columbia Gorge Community College Bond Project Updates Latest Update
The Dalles Campus · summer 2026

Investing in our college, our community, our future.

In November 2024, Gorge voters approved a capital bond to modernize Columbia Gorge Community College (CGCC). Together with Oregon state matching funds, it puts over $12 million to work at The Dalles Campus (TDC) and the Hood River Center (HRC).

About the Projects

A community investment in safe, modern learning spaces

Measure 33-111 authorized a general obligation bond to repair, modernize, and secure college facilities — while keeping the tax rate the same, with no increase to the rate district taxpayers were already paying. Passage also made the college eligible for Oregon state matching funds, stretching every local dollar further.

A portion of the bond was used to pay off the district's existing debt, which reduces long-term interest costs for taxpayers. That leaves over $12 million in combined bond proceeds and state matching funds available for campus projects. The updates and improvements grew out of a facilities planning committee that reviewed every college building and recommended the priorities below.

What the Bond Funds

Priorities guiding every project

Safer campuses

Security cameras, automatic door-locking and access control, fire-alarm upgrades, and seismic improvements to protect students and staff.

Updated building systems

Renewing aging roofs, elevators, lighting, HVAC, and other core systems for better operations, energy efficiency, technology, and accessibility at both locations.

The Projects

Where the work is happening

Bond dollars fund a schedule of projects at both locations and across college-wide systems. Week-by-week detail is in Construction Updates below.

The Dalles Campus

Roof Evaluation & Replacement

The Dalles Campus

Replacing aging roofing to protect buildings and improve energy performance.

In progress

Elevator Modernization

The Dalles Campus

Upgrading elevator equipment for reliability, safety, and accessibility.

In progress

Exterior Staircase Replacement

The Dalles Campus

Replacing exterior stairs to improve safety and access between levels.

In progress

Seismic Studies

The Dalles Campus

Evaluating building structures to guide seismic safety improvements.

In progress

Wayfinding & Signage

The Dalles Campus

New campus wayfinding and signage designed with Mayer/Reed for clearer navigation.

In progress
Hood River Center

Controls Upgrade

Hood River Center · Energy Trust

Modernizing building controls for comfort, efficiency, and smarter operations.

Complete
Program-Wide

Fire Alarm, Security & Access

TDC and HRC

Upgraded fire alarm, security cameras, and door access control for safer campuses.

In planning

HVAC Evaluation & Replacement

TDC and HRC

Assessing and replacing heating and cooling systems for efficiency and reliability.

In design

ADA Parking & Site Survey

TDC and HRC

Accessibility and parking improvements, beginning with a full site survey.

In progress

Network Upgrades

TDC and HRC

Strengthening campus network infrastructure to support modern learning technology.

In planning
Current as of the week of Aug. 17, 2026. Grinding and paving prep move to Parking Lots #1, #2 and #4 the week of Aug. 17. Expect detours and limited parking in those lots. Active summer work may also produce noise, dust, and temporary detours at The Dalles Campus.

Construction Updates

How the projects are progressing

Weekly field updates and monthly reports to the CGCC Board are summarized here as design and construction milestones are reached. Most recent first.

Progress around campus · week of Aug. 14
The completed east staircase at Building 3, with new landings, railings, and grating treads against the building.
Completed east staircase
A closer view of the finished east staircase showing the upper landing, the mid-level landing, and the new railings.
New landings and railings
The lower flight of the new staircase seen from the ground, with the finished landing and railing at the entry.
Lower flight and entry landing
The new upper landing outside the second-floor entry doors, with grating decking and railings installed.
New upper landing
Looking down the new staircase at the installed grating treads and railings, with the campus drive below.
New grating treads
Week of Aug. 17, 2026 Planned

Grinding and paving prep at Parking Lots #1, #2 and #4

Roofing, paving, and elevator work continue across campus this summer. Here's what's planned for August 17–21, and what to expect as the work moves ahead. Parking Lots #1, #2 and #4 see grinding Monday and Tuesday and paving prep Tuesday through Friday, so expect detours and limited parking all week — watch for signage and crew directions. Expect grinding and paving noise plus asphalt odor near the parking lots all week, and hot tar work at the Building 2 and Building 4 roofs Monday through Friday.

  • Roof, Building 2: tear-off Monday through Wednesday, and roofing installation Monday through Saturday.
  • Roof, Building 4: roofing installation Monday through Friday, completing Friday, with sheet metal Monday through Friday.
  • Elevator modernization: punch list this week, with the crew demobilizing the week of Aug. 24.
  • Site and paving: grinding at Parking Lots #1, #2 and #4 Monday and Tuesday, paving prep at those lots Tuesday through Friday, and excavation and rock at The Dalles parking area beginning Friday.
  • Hood River Center: crack seal, sealcoat, and stripe Thursday and Friday.
  • Coming the week of Aug. 24: Building 2 sheet metal, Building 2 HVAC, Hood River pressure wash, and the Hood River generator pad.
Week of Aug. 10, 2026 In progress

Repaving at The Dalles parking area; east stair wraps up

Paving crews are scheduled at The Dalles parking area and Parking Lot #3 Monday through Friday. Expect continued detours and limited parking in that area through the week. The east stair replacement finishes and that crew demobilizes Thursday.

  • East stair: tread and landing grating installed Monday and Tuesday, riser faces Tuesday, cleanup Wednesday, and the crew demobilizes Thursday.
  • Elevator: final inspection is scheduled this week, with the punch list to follow the week of Aug. 17 and the crew demobilizing the week of Aug. 24. Dates are tentative.
  • Roof, Building 2: roofing installation continues Monday through Saturday, with tear-off work carrying into the following week.
  • Roof, Building 4: roofing installation finishes Friday, with sheet metal installed Monday through Friday.
  • ADA pathways and parking: asphalt paving and striping at The Dalles parking area and Parking Lot #3, Monday through Friday, and concrete installation at the parking area on Monday.
  • Hood River Center: pressure washing begins Friday, continuing the following Monday.
Week of Aug. 2, 2026 Complete

Parking Lot #3 closes as paving and painting begin

Parking Lot #3 closed Tuesday, Aug. 4 while crews grind the lot ahead of repaving on Monday, Aug. 10. The main drive aisle to Parking Lot #2 stays open.

  • East stair: second-phase sandblasting Tuesday, then painting of all components Wednesday through Friday. Expect noise Tuesday.
  • West stair: joint sealants at the brick veneer column Wednesday.
  • Elevator: demolition of the existing equipment.
  • Roof, Building 2: torch-down built-up roofing on the lower roof sections at the Bookstore, with tear-off continuing on the upper roofs.
  • ADA pathways and parking: concrete continuing at The Dalles parking area, the stairs, and the Building 5 ADA work, plus grinding and paving at the parking area and Parking Lot #3.
  • An existing utility conflict along The Dalles Pathway and the ADA path from Building 3 to the connecting path is still being resolved and may affect the schedule.
Week of July 27, 2026 Complete

Stair steel, elevator fixtures, and campus concrete

Four projects are active in the field at The Dalles Campus this week.

  • East stair: joint sealants at the brick veneer column, new tread support angles, and new steel tied into the existing structure, with second-phase sandblasting Friday.
  • Elevator: hall fixtures, hall door equipment, car door equipment, and car fixtures being installed.
  • Roof: Building 4 being completed and tear-off underway at Building 2.
  • ADA pathways and parking: concrete at Buildings 2 and 4, a valley gutter and curb pour, and concrete work in The Dalles parking area.
Week of July 19, 2026 Complete

Stair demolition and elevator equipment set

A crane lifted new equipment into the elevator equipment room as stair demolition advanced.

  • West stair: joint sealants at the brick veneer column.
  • East stair: pan deck cuts, temporary fencing and storefront protection, beam install, sawcutting, first-phase sandblasting, and top-down demolition of stair pans and landings.
  • Elevator: governor, pit equipment, and hoistway equipment wrapped up; hall fixture installation began.
  • ADA and parking: Building 1 ramp concrete and sitework, Building 4 ramp demolition and sitework, and parking lot base and paving.
Week of July 12, 2026 Complete

West stair finished as elevator machine is set

Stair and elevator replacement work spread across campus, with crews mobilizing from the west staircase to the east.

  • West stair: treads and risers installed, brick cleaned and repaired, and crews mobilized to the east staircase.
  • East stair: work plan laid out with temporary fencing, protection, and interior walls so occupants would not exit through the work zone.
  • Elevator: new machine and rope mounted, new controller mounted and wired, governor set, and pit and hoistway equipment installed.
  • ADA: continuing concrete at Buildings 2 and 4 and The Dalles parking area, plus underground utility work by Building 3.
Early summer 2026 Complete

Signage awarded and ADA work moves to the field

The program shifted from design into procurement and field work across several projects.

  • Wayfinding signage advanced to fabrication, with a notice to award issued and an additional-services amendment approved to extend interior signage programming.
  • The campus ADA accessibility improvements reached a pre-construction milestone with the civil and survey teams.
  • Monthly billing and schedule-of-values reviews established for consistent, transparent reporting.
Spring 2026 Complete

Roofing package advances to bid

End-of-month updates were presented to the Board through the spring as key packages advanced.

  • The Dalles Campus roof project reached 100% construction documents and went out to bid, with addenda issued to bidders.
  • Wayfinding design and additional-services approvals moved forward.
  • Civil design services engaged to support site and accessibility work.
Winter 2025-26 Complete

Design underway across priority projects

With contracts in place, design teams began developing the first bond-funded improvements and the program settled into a steady monthly reporting rhythm.

  • Design meetings launched for early priority projects.
  • A year-end program update was issued summarizing progress to date.
  • Alternative contracting method findings completed to enable efficient project delivery.
Fall 2025 Complete

Program launch and contracts

HMK Company was engaged to manage the capital bond program. Initial professional-services contracts were approved and issued, and the college's bond communications plan — including newsletters and this landing page — was established.

Nov. 5, 2024 Milestone

Voters approve Measure 33-111

Gorge voters passed the capital bond, launching the improvement program and unlocking Oregon state matching funds. Proceeds also retired the district's existing debt, lowering long-term interest costs.

Draft for CGCC review. Progress summaries are drawn from HMK's weekly field updates and monthly end-of-month program reports, plus public bond information. Exact figures, dates, and project scopes can be confirmed and expanded before this page goes live.

Stay Informed

Follow the progress

Bond program updates are shared with the community through weekly field notices, monthly and quarterly newsletters, and reports at public Board of Education meetings. Have a question about a project?

Ask a Question